sprint-planning

द्वारा anthropic

स्प्रिंट की योजना बनाएं — कार्य का दायरा तय करें, क्षमता का अनुमान लगाएं, लक्ष्य निर्धारित करें और एक स्प्रिंट योजना तैयार करें। नए स्प्रिंट की शुरुआत करते समय, बैकलॉग को टीम के विरुद्ध आकार देते समय उपयोग करें…

npx skills add https://github.com/anthropics/knowledge-work-plugins --skill sprint-planning

/sprint-planning

If you see unfamiliar placeholders or need to check which tools are connected, see CONNECTORS.md.

Plan a sprint by scoping work, estimating capacity, and setting clear goals.

Usage

/sprint-planning $ARGUMENTS

How It Works

┌─────────────────────────────────────────────────────────────────┐
│                    SPRINT PLANNING                                 │
├─────────────────────────────────────────────────────────────────┤
│  STANDALONE (always works)                                       │
│  ✓ Define sprint goals and success criteria                     │
│  ✓ Estimate team capacity (accounting for PTO, meetings)        │
│  ✓ Scope and prioritize backlog items                           │
│  ✓ Identify dependencies and risks                              │
│  ✓ Generate sprint plan document                                │
├─────────────────────────────────────────────────────────────────┤
│  SUPERCHARGED (when you connect your tools)                      │
│  + Project tracker: Pull backlog, create sprint, assign items   │
│  + Calendar: Account for PTO and meetings in capacity           │
│  + Chat: Share sprint plan with the team                        │
└─────────────────────────────────────────────────────────────────┘

What I Need From You

  • Team: Who's on the team and their availability this sprint?
  • Sprint length: How many days/weeks?
  • Backlog: What's prioritized? (Pull from tracker, paste, or describe)
  • Carryover: Anything unfinished from last sprint?
  • Dependencies: Anything blocked on other teams?

Output

## Sprint Plan: [Sprint Name]
**Dates:** [Start] — [End] | **Team:** [X] engineers
**Sprint Goal:** [One clear sentence about what success looks like]

### Capacity
| Person | Available Days | Allocation | Notes |
|--------|---------------|------------|-------|
| [Name] | [X] of [Y] | [X] points/hours | [PTO, on-call, etc.] |
| **Total** | **[X]** | **[X] points** | |

### Sprint Backlog
| Priority | Item | Estimate | Owner | Dependencies |
|----------|------|----------|-------|--------------|
| P0 | [Must ship] | [X] pts | [Person] | [None / Blocked by X] |
| P1 | [Should ship] | [X] pts | [Person] | [None] |
| P2 | [Stretch] | [X] pts | [Person] | [None] |

### Planned Capacity: [X] points | Sprint Load: [X] points ([X]% of capacity)

### Risks
| Risk | Impact | Mitigation |
|------|--------|------------|
| [Risk] | [What happens] | [What to do] |

### Definition of Done
- [ ] Code reviewed and merged
- [ ] Tests passing
- [ ] Documentation updated (if applicable)
- [ ] Product sign-off

### Key Dates
| Date | Event |
|------|-------|
| [Date] | Sprint start |
| [Date] | Mid-sprint check-in |
| [Date] | Sprint end / Demo |
| [Date] | Retro |

Tips

  1. Leave buffer — Plan to 70-80% capacity. You will get interrupts.
  2. One clear sprint goal — If you can't state it in one sentence, the sprint is unfocused.
  3. Identify stretch items — Know what to cut if things take longer than expected.
  4. Carry over honestly — If something didn't ship, understand why before re-committing.

anthropic की और Skills

comps-analysis
anthropic
हमेशा इस डेटा स्रोत पदानुक्रम का पालन करें:
official
analyzing-financial-statements
anthropic
यह कौशल निवेश विश्लेषण के लिए वित्तीय विवरण डेटा से प्रमुख वित्तीय अनुपात और मीट्रिक की गणना करता है।
official
applying-brand-guidelines
anthropic
यह कौशल सभी जनरेट किए गए दस्तावेज़ों में रंग, फ़ॉन्ट, लेआउट और संदेश सहित एक समान कॉर्पोरेट ब्रांडिंग और स्टाइलिंग लागू करता है।
official
cookbook-audit
anthropic
एन्थ्रोपिक कुकबुक नोटबुक का एक रूब्रिक के आधार पर ऑडिट करें। जब भी नोटबुक समीक्षा या ऑडिट का अनुरोध किया जाए, इसका उपयोग करें।
official
creating-financial-models
anthropic
यह कौशल डीसीएफ विश्लेषण, संवेदनशीलता परीक्षण, मोंटे कार्लो सिमुलेशन और निवेश के लिए परिदृश्य योजना के साथ एक उन्नत वित्तीय मॉडलिंग सूट प्रदान करता है…
official
action-creator
anthropic
उपयोगकर्ता-विशिष्ट एक-क्लिक कार्रवाई टेम्पलेट बनाता है जो चैट इंटरफ़ेस में क्लिक करने पर ईमेल संचालन निष्पादित करते हैं। उपयोग करें जब उपयोगकर्ता पुन: प्रयोज्य कार्रवाइयाँ चाहता है...
official
docx
anthropic
दस्तावेज़ निर्माण, संपादन और विश्लेषण की व्यापक क्षमता, जिसमें ट्रैक किए गए परिवर्तन, टिप्पणियाँ, फ़ॉर्मेटिंग संरक्षण और टेक्स्ट निष्कर्षण का समर्थन शामिल है। जब Claude…
official
executive-briefing
anthropic
शोध निष्कर्षों को कार्यकारी-तैयार ब्रीफिंग में बदलता है। जब उपयोगकर्ता 'executive', 'briefing', 'C-suite', 'board',… का उल्लेख करता है तो स्वचालित रूप से सक्रिय हो जाता है।
official